After the award: assessment summaries, standstill and feedback
After a Procurement Act tender result: the assessment summary, the 8 working day standstill, how to query or challenge it, and how to score higher next time.
By OneTender team9 min read

In short
- After an above-threshold competitive tendering procedure, every supplier with an assessed tender gets an assessment summary before the contract award notice.
- Unless the contract is light touch, that notice starts a standstill of at least 8 working days, and the buyer can't enter into the contract until it ends.
- A claim issued and notified during standstill suspends the contract automatically. Most claims must start within 30 days of when you knew, or ought to have known, the grounds.
- Framework call-offs and below-threshold contracts get neither an assessment summary nor a mandatory standstill.
- Win or lose, log every score and reason by question, and rewrite the answers that lost marks.
For an above-threshold contract awarded through a competitive tendering procedure, every supplier whose tender was assessed gets an assessment summary before the buyer publishes its contract award notice (section 50 (opens in a new tab)). Unless the contract is light touch, publishing that notice starts a standstill of at least 8 working days (section 51 (opens in a new tab)). If you issue a claim and notify the buyer during standstill, the buyer is automatically stopped from entering into the contract (section 101 (opens in a new tab)). Claims generally must start within 30 days of when you knew, or ought to have known, the grounds (section 106 (opens in a new tab)).
What happens between the decision and the contract
This is the sequence after an above-threshold competitive tendering procedure. Standstill counts working days; the other deadlines count calendar days.
| Step | When | What it means for you |
|---|---|---|
| Assessment summaries | After the award decision, sent to every supplier with an assessed tender at the same time | Your scores and the reasons, plus the winning tender's scores if you lost |
| Contract award notice | Published on Find a Tender (opens in a new tab), often the same day the summaries go out | Names the supplier the buyer intends to contract with and the last day of standstill |
| Standstill | At least 8 working days, beginning with the day the notice is published | Your window to raise concerns, or to issue a claim that suspends the contract |
| Contract entered into | From working day 9 at the earliest, later if the standstill is longer or a claim suspends it | The buyer doesn't have to sign straight away |
| Contract details notice | Within 30 days of entering into the contract (120 days for light touch contracts) | Public confirmation that the contract exists |
| Copy of the contract | Within 90 days for contracts over £5 million (180 days for light touch contracts) | The contract itself, which may be redacted |
Weekends and bank holidays in any part of the UK don't count as working days, and the day the notice is published is day one, however late it goes up. The standstill guidance (opens in a new tab) works through a Christmas example: a notice published on Wednesday 19 December lets the buyer enter into the contract on Friday 4 January. The 30 and 90 day periods after signing are calendar days (opens in a new tab).
What an assessment summary must tell you
Summaries go to every supplier with an assessed tender at the same time and before the contract award notice, so you have the whole standstill to read yours. They can arrive by email or through the buyer's e-tendering system.

Regulation 31 (opens in a new tab) of the Procurement Regulations 2024 sets out what each summary must contain, and the Assessment Summaries guidance (opens in a new tab) explains it:
- The award criteria, in full or summarised with each criterion's title, weighting, assessment method and available scores, plus where to find the full version.
- Your score for every criterion and sub-criterion, with any sub-totals and your total.
- Why you got each score, by reference to your own tender. The guidance says a buyer can't just repeat the criterion and say the tender failed to demonstrate it, and calls explaining why a higher score wasn't reached best practice.
- If you lost: the winning tender's scores and explanations, and any further reason you weren't chosen, such as missing a minimum score.
There is no side-by-side comparison, but reading your scores next to the winner's shows the gap, and the guidance says buyers should name the winner where that isn't a significant burden. Buyers may withhold sensitive commercial details of the winning tender under section 94 (opens in a new tab) only where there is an overriding public interest in doing so, and must tell you they have. The guidance still expects each of the winner's scores to be explained, and blanket confidentiality claims to be discouraged (paragraphs 28, 32 and 33).
Nothing in the Act requires a debrief meeting. The guidance says buyers may add general feedback to help with future tenders, which may be particularly useful for SMEs, though it isn't a legal requirement (paragraph 36). If your tender was knocked out before the final assessment stage, you get no summary, but buyers should tell you in writing as soon as reasonably possible (paragraph 11).
When there is no assessment summary or standstill
Not every award follows the full sequence. Annex A of the standstill guidance (opens in a new tab) lists every case, and these are the common ones:
| Type of award | Assessment summary? | Mandatory standstill? |
|---|---|---|
| Competitive tendering procedure above the threshold, including setting up a framework | Yes | Yes |
| Light touch contract after a competitive procedure | Yes | No |
| Call-off under a framework, with or without a mini-competition | No | No |
| Contract awarded under a dynamic market | Yes | No |
| Joining a dynamic market | No, as it isn't a contract | No |
| Direct award for extreme and unavoidable urgency | No | No |
| Most other direct awards | No | Yes |
| Below-threshold contract | No | No |
Without a mandatory standstill, the buyer can still set a voluntary one of at least 8 working days, and a claim issued and notified during it still suspends the contract. For call-offs, the assessment summaries guidance says giving summaries anyway is best practice (paragraph 41).
Below the threshold, the remedies in Part 9 of the Act don't apply: the Remedies guidance (opens in a new tab) says the below-threshold duties may instead be subject to judicial review (paragraph 15). Our guide to below-threshold works tenders covers how those procurements run.
Two routes sit outside these rules. Devolved Scottish authorities (opens in a new tab) generally follow Scotland's own procurement law, not the Act. Health care services bought in England under the Provider Selection Regime follow its own rules: where an award has a standstill (opens in a new tab), you can make written representations to the buyer during it, as our Provider Selection Regime guide explains.
Reading your scores like an evaluator
Each reason should point to something in your tender, so the summary doubles as a marking guide. Start with the biggest gaps on the heaviest weightings.

| What the summary says | What it usually means | What to change next time |
|---|---|---|
| Lacked evidence | Claims without proof | Add measurable outcomes, named roles and a case study from a similar contract |
| Did not address all parts of the question | A requirement or sub-question was missed | Answer in the question's own order, with a heading for each part |
| Generic, or not specific to this contract | It could suit any buyer | Use the buyer's sites, volumes, service users and risks |
| Limited detail on how | You said what, not how, who or when | Give the method, the responsible role and the timescale |
| Met the requirements | Compliant, but nothing more | Show what goes beyond the specification, and why it matters |
| Commitments not measurable | No numbers, dates or reporting | Give numbers, dates and how you'll report each one |
If a reason doesn't match the tender's scoring guide, ask the buyer in writing which part of your tender the evaluator relied on.
Asking questions and challenging
Start with a written question to the buyer, sent quickly: name the criterion, quote the reason given and point to the part of your tender you think was missed. The Remedies guidance (opens in a new tab) encourages buyers to engage with suppliers who raise concerns and to act in time, extending the standstill where needed rather than forcing a claim (paragraph 59). An extended standstill means a re-published contract award notice (paragraph 18).
The formal route is a claim for breach of statutory duty. These points matter most:
- Automatic suspension: start proceedings and notify the buyer during standstill, and it can't enter into the contract. After standstill, you would need to ask the court for an injunction.
- 30 days: most claims must start within 30 calendar days, beginning with the day you first knew, or ought to have known, the grounds. The guidance says that is usually when you get information that lets you identify the breach (paragraph 47).
- Extensions: the court can extend the 30 days only for a good reason, and never beyond 3 months from that same day (paragraph 49).
- Where: the guidance notes that the Technology and Construction Court deals with public procurement claims (paragraph 50).
- What a court can do: before the contract is signed, set aside the decision, order a re-assessment or award damages; after it, award damages, and set the contract aside only in limited conditions (paragraphs 27 to 35).
For a review rather than a court case, the Public Procurement Review Service (opens in a new tab) (PPRS) takes supplier concerns about a specific procurement through an online form (opens in a new tab). The issue must have happened within the last 2 years, it can be at any stage, and its recommendations are non-binding. A referral doesn't trigger the automatic suspension: only court proceedings issued and notified during standstill do.
If you won the contract
- Contract details notice: the buyer publishes it within 30 days of entering into the contract (120 for light touch contracts), and for contracts over £5 million publishes a copy of the contract within 90 days (section 53 (opens in a new tab)).
- KPIs: before entering into a contract over £5 million, the buyer must set at least three key performance indicators and publish them (section 52 (opens in a new tab)). It then assesses your performance against them at least once every 12 months and publishes the result (section 71 (opens in a new tab)). Frameworks and light touch contracts are exempt.
- Breach and poor performance: if a breach leads to termination, damages or a settlement, or you fail to improve after a proper opportunity, the buyer must publish that within 30 days (except on light touch contracts), and such a notice is a discretionary exclusion ground in future tenders (Schedule 7, paragraph 12 (opens in a new tab)).
- Payment: public contracts carry an implied term that valid, undisputed invoices are paid within 30 days, and the buyer must tell you without undue delay if it disputes one or thinks it invalid (section 68 (opens in a new tab)). A valid invoice needs at least your name, a description of what you supplied, the sum and a unique number.
- Mobilisation: plan staffing, insurance and KPI reporting during standstill, but avoid costs you can't recover if a claim suspends the contract.
Turn feedback into your next win
Win or lose, the summary is free marking. Use it the same week:
- Keep a score log by question: the criterion, its weighting, your score, the winner's score and the reason. After a few tenders it shows where you keep losing marks.
- Update your answer library: rewrite the answers that lost marks while the reasons are fresh, and keep the high scorers as starting points.
- Request a call: ask for general feedback on your two or three weakest answers. It isn't required, but buyers may give it.
- Reuse what scored: note the evidence and commitments the evaluators credited, and use them again where they fit.
When the result arrives
- Note the standstill end date and the 30-day claim deadline on the day the result arrives
- Check the summary gives a score and a reason for every criterion and sub-criterion
- Compare your scores with the winner's, criterion by criterion, to find the biggest gaps
- Send any question or concern to the buyer in writing before the standstill ends
- Log every score and reason in your score log, question by question
- Ask the buyer for a short feedback call on your two or three weakest answers
- Rewrite the answers that lost marks and file them in your answer library
- If you won, diary the KPIs, reporting dates and invoice requirements in the contract
Where OneTender fits
After you submit, OneTender keeps tracking the bid. It picks up the contract award, contract details and procurement termination notices for that tender from Find a Tender, and shows the standstill on the bid as a day count, such as day 3 of 8, with its end date. It also tracks the buyer's requests and their due dates. It suggests the outcome, and a person on your team marks the bid won or lost. It never sends anything to a buyer.
Sources
- Procurement Act 2023, section 50: contract award notices and assessment summaries (opens in a new tab) legislation.gov.uk
- Procurement Act 2023, section 51: standstill periods on the award of contracts (opens in a new tab) legislation.gov.uk
- Procurement Act 2023, section 52: key performance indicators (opens in a new tab) legislation.gov.uk
- Procurement Act 2023, section 53: contract details notices and publication of contracts (opens in a new tab) legislation.gov.uk
- Procurement Act 2023, section 68: implied payment terms in public contracts (opens in a new tab) legislation.gov.uk
- Procurement Act 2023, section 71: assessment of contract performance (opens in a new tab) legislation.gov.uk
- Procurement Act 2023, section 94: general exemptions from duties to publish or disclose information (opens in a new tab) legislation.gov.uk
- Procurement Act 2023, section 101: automatic suspension of the entry into or modification of contracts (opens in a new tab) legislation.gov.uk
- Procurement Act 2023, section 106: time limits on claims (opens in a new tab) legislation.gov.uk
- Procurement Act 2023, Schedule 7, paragraph 12: breach of contract and poor performance (opens in a new tab) legislation.gov.uk
- Procurement Regulations 2024, regulation 31: assessment summaries (opens in a new tab) legislation.gov.uk
- Cabinet Office guidance: assessment summaries (opens in a new tab) gov.uk
- Cabinet Office guidance: contract award notices and standstill (opens in a new tab) gov.uk
- Cabinet Office guidance: contract details notices (opens in a new tab) gov.uk
- Cabinet Office guidance: remedies (opens in a new tab) gov.uk
- Cabinet Office guidance: procurement oversight (opens in a new tab) gov.uk
- Cabinet Office guidance: devolved contracting authorities (opens in a new tab) gov.uk
- Health Care Services (Provider Selection Regime) Regulations 2023, regulation 12: the standstill period (opens in a new tab) legislation.gov.uk
- GOV.UK: Procurement Compliance and Oversight, including the Public Procurement Review Service (opens in a new tab) gov.uk
- GOV.UK Forms: raise a concern with the Public Procurement Review Service (opens in a new tab) submit.forms.service.gov.uk
- Find a Tender (central digital platform) (opens in a new tab) find-tender.service.gov.uk
This guide is general information, not legal advice. Check the buyer's documents and the official guidance for your procurement.